Updated
For Business owners, finance directors, directors and in-house legal teams pursuing or defending a business invoice claim in England and Wales.
Jump to a section
The short answer: classify the invoice before escalating
A recovery route should follow the evidence, not the age of the invoice. First decide whether the customer accepts liability and has simply not paid, whether it disputes performance, price or the contracting party, or whether it advances a counterclaim or set-off. Those categories can lead to very different next steps.
For an apparently clear business debt, a focused pre-action letter followed, if needed, by a money claim may be proportionate. For a genuine quality, valuation or set-off dispute, the aim is to define the issue and the evidence before spending heavily on pressure or proceedings. A default judgment is available only if the CPR conditions are met; it is not the automatic consequence of sending an invoice.8
Key points
- Prove the contract, the legal entities, performance, agreed price, due date and any credits before calculating interest.
- A B2B invoice does not bring the Debt Claims Protocol into play unless the debtor is a sole trader, but proportionate pre-action conduct still matters.6
- Statutory late-payment interest is a regime with conditions. A contractual interest clause must be considered, not ignored.1
- Track allocation and recoverable-cost rules can make a technically sound low-value claim commercially unattractive.9 11
- Insolvency procedure is not the ordinary device for deciding a substantially disputed invoice.
First, establish who owes what
Start with the contract, rather than the accounts ledger. An invoice is important evidence, but it does not itself answer who made the bargain, what was promised or whether a credit, retention, variation or counterclaim changes the balance. This is especially important in group structures, construction or service chains, and arrangements involving a trading name.
Prepare a short claim map before writing the letter of claim:
- Parties and authority. Record the supplier's and purchaser's full legal names, company numbers where relevant, the signatory or buyer, any assignment, and whether a director or parent actually gave a separate guarantee.
- Obligation and price. Identify the signed contract, purchase order, quotation, terms incorporated by reference, variations, payment clause and invoice currency.
- Performance. Match each invoice to delivery notes, timesheets, acceptance records, emails, milestones and any complaint or remedial work. Preserve native files and a clean chronology.
- Balance. Reconcile the principal sum against payments, credit notes, discounts, retentions and a clear schedule of interest and compensation.
- Defence matrix. Put each asserted point in one line: the allegation, contractual clause or factual basis, documents supporting it, amount said to be withheld, and the supplier's answer.
- Recovery reality. Consider the customer's assets, continuing relationship, security, limitation position, insurance and the value of a judgment that may later need enforcement.
A claim for a commercial invoice normally arises under a contract for goods or services where both parties act in the course of business. That is the gateway to the statutory late-payment regime; it does not cover a contract of employment or apprenticeship, and it has other express exclusions.1
A buyer may describe a response as a “set-off” when it says that its own cross-claim should reduce what it pays. The label is not decisive. Read any express set-off or payment-withholding clause first, then test the factual and legal basis of the alleged cross-claim. A defective-performance allegation may be a real dispute on the invoice, a separate damages claim, or neither. The right response is a particularised request for the alleged defects, dates, notices, loss calculation and supporting material, not an assumption that the whole account is either conceded or defeated.
For the wider contractual analysis behind that exercise, see the companion guide on assessing a commercial contract dispute.
When can statutory late-payment remedies be claimed?
The Late Payment of Commercial Debts (Interest) Act 1998 implies a right to statutory interest into qualifying commercial contracts. The debt must be for all or part of the contract price under a contract within the Act.1 Interest starts on the day after the statutory “relevant day”. An agreed payment day will commonly matter, but the statutory provisions also address the absence of an agreed date, public-authority purchasers and acceptance or verification procedures. The calculation should therefore be tied to the actual contract and chronology, rather than simply counting from the printed invoice date.15
For B2B transactions, the published statutory rate is 8% plus the Bank of England base rate. The applicable base rate and the number of days must be checked for the relevant period; a demand should show the principal, start date, rate, daily rate and accumulated amount rather than present one unexplained total.5
Once statutory interest begins, section 5A also provides a fixed sum of £40 for a qualifying debt below £1,000, £70 for one from £1,000 to below £10,000, and £100 for one of £10,000 or more. If reasonable recovery costs exceed that fixed sum, the supplier may claim the difference. That is not a blank cheque for disproportionate expenditure: record the work, cost and why it was reasonably incurred.3
Do not automatically add statutory interest to contractual interest. Section 8 makes terms excluding or varying statutory interest ineffective unless the contractual or overall late-payment remedy is “substantial”; where the parties agree a substantial contractual remedy, the debt does not carry statutory interest unless they agree otherwise.4 The sensible presentation is to plead the correct contractual basis first, and only advance an alternative statutory calculation where the contract and facts permit it. A clause fixing a low rate is not safely assessed by its label alone.
What pre-action route applies to a B2B invoice?
The Pre-Action Protocol for Debt Claims is often cited in invoice correspondence, but its scope is narrower than many assume. It applies where a business claims a debt from an individual, including a sole trader; it expressly does not apply to business-to-business debts unless the debtor is a sole trader.6
For an ordinary company-to-company debt to which no specialist protocol applies, the Practice Direction – Pre-Action Conduct and Protocols applies. Its objectives are to exchange enough information to understand positions, make decisions, explore settlement or ADR and reduce costs. A concise letter should state the legal and factual basis, the remedy and a calculation. A straightforward response is normally expected within 14 days, while a very complex case may justify longer. Key documents should be exchanged proportionately.7
This is not a rule that every late invoice requires a long formal protocol exchange. Nor is it a reason to issue first and ask questions later. A proportionate letter for a disputed invoice will normally identify the invoice schedule, contract, performance relied upon, interest basis, what is said in response to the alleged dispute, the documents enclosed, a payment or substantive-response deadline, and a genuine invitation to resolve the defined issue. The court may take material non-compliance or an unreasonable refusal to consider ADR into account when managing the case or making costs and interest orders.7
A limitation deadline is separate from pre-action correspondence and negotiations. Neither an enquiry nor ADR automatically stops time. If the invoice is old, identify the applicable deadline at once; the companion article on commercial limitation and contractual time bars addresses that risk in more detail.
Which court route is proportionate?
A defended invoice claim is not made simpler by calling it “debt collection”. The possible routes should be compared against the evidence, amount, likely defence, costs, time and enforceability.
No response after a properly served claim. CPR Part 12 defines default judgment as judgment without trial where the defendant has failed to file an acknowledgment of service or a defence. Rule 12.3 also requires the relevant time to have expired and prevents default judgment in specified situations, including where the whole claim has been satisfied or a defendant has admitted the money claim and asked for time to pay.8
Defence with no real evidential foundation. Summary judgment is a distinct application, not a substitute for default judgment. Under CPR 24.3, the court may decide a claim, defence or issue without trial only where the opposing party has no real prospect of success and there is no other compelling reason for a trial.12 A bare denial does not answer a well-documented claim, but a live factual dispute about performance, variation or set-off may make a summary application costly and unsuitable. The related summary judgment guide considers that decision in depth.
Allocation and costs. For a straightforward monetary claim, the small claims track is normally the starting point up to £10,000. The fast track is normally the next route for claims up to £25,000 where, among other matters, trial and expert evidence are suitably limited. The intermediate track can be the normal track up to £100,000 only if its further suitability conditions are met; otherwise the multi-track may be normal.9
Those thresholds are not a costs promise. On the small claims track, CPR 27.14 sharply limits recoverable costs, save for specified items such as fixed issuing costs, court fees and, in limited circumstances, unreasonable conduct.10 In the fast and intermediate tracks, CPR Part 45 has fixed-cost regimes with their own scope, stages, complexity bands and permitted disbursements.11 A recovery plan should therefore be costed before issue, including the risk that a successful party will not recover every pound spent. For settlement and offer strategy, see mediation, Part 36 and costs.
Why a disputed invoice is not an insolvency lever
A statutory demand and winding-up process address company insolvency; they are not an ordinary alternative forum for trying an invoice dispute. Section 123 of the Insolvency Act 1986 includes a deeming provision where a company owing more than £750 has, after a prescribed written demand at its registered office, neglected for three weeks to pay, secure or compound the sum to the creditor's reasonable satisfaction. It also contains cash-flow and balance-sheet tests.14
That statutory threshold does not establish the contractual liability. In Mann v Goldstein [1968] 1 WLR 1091, Ungoed-Thomas J explained that where the debt is disputed on substantial, rather than frivolous, grounds, winding-up proceedings should not be used to determine whether the petitioner is a creditor; the judgment describes that use as an abuse of process (pp 1096 and 1099).13 A party considering a demand or facing one should obtain prompt case-specific advice, particularly where there is a genuine contractual defence, set-off, cross-claim, payment issue or solvency concern.
Worked hypothetical: divide the clear debt from the live issue
Scenario. A design supplier invoices a corporate customer £18,000 under a signed purchase order with 30-day terms. The customer paid earlier stages but now says that £6,000 of remedial work is required. It sends no supporting estimate and its email refers to a different group company. The contract contains a 5% contractual late-interest clause.
A proportionate approach.
- Confirm which company placed the order and received the work. Do not sue a trading-name contact or parent simply because it was copied into correspondence.
- Put the £18,000 ledger beside the purchase order, specification, approval emails, delivery/acceptance evidence and any credit. Ask the customer to identify the alleged defects, contractual notice, remedial scope, causation and £6,000 calculation.
- Treat the £12,000 balance and the £6,000 complaint separately in the correspondence. That does not decide whether a set-off is legally available, but it stops the real issue being obscured by an all-or-nothing demand.
- Check whether the 5% clause supplies a substantial overall remedy under section 8 before claiming statutory interest as well. Show the calculation and reserve only remedies that are properly available.4
- Send a concise, proportionate pre-action letter. Because both parties are companies, do not describe the Debt Claims Protocol as governing the exchange. Invite a short meeting or mediation if the factual issue is capable of resolution.6
- If no proper answer arrives, assess a money claim and the evidence for default judgment. If the defect dispute becomes supported and material, budget for a defended fast-track analysis rather than assuming the label “invoice” produces a quick result.8
The outcome will turn on the actual contract, documents and evidence. The example is not a substitute for checking whether an express no-set-off clause, acceptance term, limitation of liability, dispute-resolution clause or insolvency event changes the position.
What should an in-house team give a commercial barrister?
The most useful instruction is a decision paper, not an unfiltered email archive. For a direct access commercial barrister or counsel instructed alongside an in-house legal team, it should identify the commercial decision sought: for example, whether to demand payment, accept a payment plan, pursue the undisputed balance, seek an early court determination, settle, or preserve a relationship.
Include the executed contract and terms, purchase orders, invoice and payment schedule, a one-page chronology, key correspondence in native form where possible, a party/guarantee note, and a dispute matrix. State the interest calculation assumed, the limitation date being worked to, known assets or enforcement intelligence, desired outcome, cost sensitivity and who holds authority to settle. Ask defined questions: liability, set-off, interest, the content of the letter, merits of an application, or advocacy at a hearing.
Keane Davison is a self-employed Public Access barrister, a tenant at and clerked by The Barrister Group. Subject to competence, conflicts, suitability and availability, he may consider advice, drafting and appropriate advocacy. He is not authorised to conduct litigation, so a client or authorised solicitor remains responsible for issuing, filing, service, litigation administration and deadlines. The commercial law service page and Public Access information explain the route; any accepted work proceeds only under a written scope, fixed-fee quote plus VAT, signed terms and payment through chambers-verified details.
FAQs
Does the Debt Claims Protocol apply to every unpaid invoice?
No. It applies to a business claiming payment from an individual, including a sole trader, and excludes business-to-business debts unless the debtor is a sole trader. A company-to-company invoice dispute ordinarily falls under the general pre-action practice direction unless another specialist protocol applies.6
Can I add 8% statutory interest to the invoice?
Possibly, but only after checking that the Act applies, the debt is qualifying, when the relevant day fell, and the contract's late-payment clause. The B2B statutory rate is 8% plus Bank of England base rate, but a substantial contractual late-payment remedy changes the statutory position under section 8.1 4
If the customer ignores the claim form, is judgment automatic?
No. A claimant must take the required step to obtain judgment, and CPR 12.3 conditions must be satisfied. The time for acknowledging service or defending must have expired, and matters such as payment, an admission with a request for time to pay, or an outstanding strike-out or summary-judgment application can prevent default judgment.8
Can a statutory demand make a customer pay a disputed invoice?
It may have serious consequences and is not a routine debt-collection letter. The Insolvency Act has a statutory demand route, but Mann v Goldstein illustrates why winding-up process is not the proper mechanism for deciding a debt disputed on substantial grounds.13
Take the next step with a decision-ready file
If the invoice has moved beyond ordinary credit control, prepare the claim map and dispute matrix before committing to a route. A focused opinion, letter, draft pleading or advocacy instruction can then be scoped around the actual commercial decision. For an appropriate commercial enquiry, use the commercial contact route and review the fees information. An enquiry does not pause any deadline or create an accepted instruction.
Scope, jurisdiction and research date
This article is a general account of the law and court procedure of England and Wales, researched to 28 October 2026. It does not determine the governing law, jurisdiction, arbitration clause, limitation date, contractual notice requirements or enforcement prospects in any particular matter. CPR, practice directions, court fees and interest rates can change; those matters should be checked against the current materials before action is taken.
Sources
- Late Payment of Commercial Debts Interest Act 1998, section 2 – contracts to which the Act applies
- Late Payment of Commercial Debts Interest Act 1998, section 3 – qualifying debt
- Late Payment of Commercial Debts Interest Act 1998, section 5A – fixed compensation and reasonable recovery costs
- Late Payment of Commercial Debts Interest Act 1998, section 8 – contractual substantial remedy
- GOV.UK guidance – interest on late commercial payments
- Pre-Action Protocol for Debt Claims, paragraphs 1.1 to 1.4
- Practice Direction – Pre-Action Conduct and Protocols, paragraphs 2 to 17
- CPR Part 12 – default judgment, especially rules 12.1 to 12.4
- CPR Part 26 – allocation and track scope, especially rule 26.9
- CPR Part 27 – small claims costs, rule 27.14
- CPR Part 45 – fast and intermediate track fixed costs, rules 45.43 to 45.50
- CPR Part 24 – summary judgment, especially rule 24.3
- Mann v Goldstein [1968] 1 WLR 1091 – retrievable report of judgment
- Insolvency Act 1986, section 123 – inability to pay debts
- Late Payment of Commercial Debts Interest Act 1998, section 4 – relevant day and interest period
Start with a short outline.
Read how direct instruction works. An enquiry does not pause a deadline or create an accepted instruction.
How to enquire